School Building Demolition — Stella Maris, Shellharbour

Single-storey brick and tile school building at Stella Maris, Shellharbour, before demolition
The building at Stella Maris before demolition.
LocationStella Maris Catholic School, Shellharbour
ClientCatholic Education Diocese of Wollongong
CompletedSeptember 2025
ScopeDemolition of a single-storey brick and tile building, a temporary building, a covered walkway and concrete hardstands; site levelled
RecycledAround 85% of material by weight

The Catholic Education Diocese of Wollongong engaged DemoEx to demolish an old single-storey brick and tile building at Stella Maris Catholic School in Shellharbour, along with a temporary building, a covered walkway and the concrete hardstands around them.

Working beside an operating school

The school stayed open for the whole job. We separated the work area from the school with temporary fencing and set up our own site entry, so our trucks and machines never shared access with students, staff or parents. SafeWork NSW and the neighbours were notified in writing before work started, and a site-specific demolition control plan was in place for the duration.

DemoEx banner on the temporary fence separating the demolition site from the school
Temporary fencing kept the work area separate from the operating school.

Strip-out first

Before any machine work, our crew cleared out the furniture and contents and stripped the building back to its frame. The roof tiles came off next and went to recycling.

School building interior stripped back to the frame before demolition
Stripped back to the frame before any machine work.
Roof of the school building being stripped, Shellharbour
Stripping the roof, with the school carrying on around us.

An unexpected asbestos find

During the strip-out, our crew found vinyl floor tiles and bituminous underlay in the music room that hadn’t been identified before the job. Work in that area stopped and samples went to an accredited laboratory, which confirmed chrysotile asbestos. DemoEx holds its own Class B asbestos removal licence (AD214187), so our crew removed it under our own licence before demolition carried on.

Vinyl floor tiles in the music room found to contain asbestos
The music room floor tiles — tested positive for asbestos and removed by our licensed crew.

Demolition and recycling

With the building stripped and the asbestos gone, we demolished the frame, the covered walkway and the temporary building, then broke out the concrete hardstands. Everything was separated on site so it could be recycled. The weighbridge dockets show:

  • About 127 tonnes of concrete, brick and roof tile to a recycling facility
  • About 9 tonnes of timber to an organics recycler
  • 2.3 tonnes of steel to a metal recycler

That’s around 85% of everything that left the site, by weight.

Covered walkway frame being demolished at Stella Maris
The covered walkway coming down.
Timber frame of the school building after strip-out
The building frame after strip-out.
Bin of roof tiles separated for recycling
Roof tiles separated for recycling.

The result

The building, walkway and hardstands gone, holes filled and the site bladed off level, ready to hand back to the school.

Excavator levelling the cleared site at Stella Maris, Shellharbour
The site cleared and levelled.